Every week we have a field crew collect and add data to a geodatabase throughout the week. At the end of the week the Supervisor wants an excel spreadsheet of all the data collected in that week.
I have a workspace that runs FME every Monday to collect the weeks worth of data. Right now, I use a tester transformer and I pre set the dates for the following week so when the workspace runs, I have the correct weeks' worth of data. We have field in the geodatabase that collects the date the asset was collected. Then I have task schedular set to run the workspace.
My question is, is there a way to pre set the dates instead of me re-setting them every week? I have tried using Datetimecalculator but I can't seem to get the parameters right.