I'm trying to keep the highest date in a range, and each of these has the same reference number. For example - "Reference Number 1 has 8 dates and we need to keep the highest date for Reference 1", but repeat a few thousand times.

 

I've had a method which worked before using Adjacent Attributes and sorting, but it doesn't seem to be working here. The dates are input in the %Y%m%d format (ie. 20120301) which I had hoped would make sorting easier.

 

I didn't know, after a long search and trying methods out, if anyone had any pointers on how to achieve this highest date business?

 

Thank you

3 replies

nielsgerrits
VIP

StatisticsCalculator, group by Reference Number, Analyze date field (%y%m%d), Maximum Attribute is highest date. Complete outputport.

It should also work in the Excel way, with sorting and adjacent attributes. This is probably a less memory intense solution. But the StatisticCalculator is easier to configure.


ebygomm
Influencer
Forum|alt.badge.img+31
  • Influencer
  • January 13, 2021

Sorting in reverse order and then a duplicate filter should work here. The duplicate filter will output the feature with the highest date for each reference number from the unique port


joe.fme
Contributor
Forum|alt.badge.img+4
  • Author
  • Contributor
  • January 14, 2021
nielsgerrits wrote:

StatisticsCalculator, group by Reference Number, Analyze date field (%y%m%d), Maximum Attribute is highest date. Complete outputport.

It should also work in the Excel way, with sorting and adjacent attributes. This is probably a less memory intense solution. But the StatisticCalculator is easier to configure.

Edit - just seen it in the "Complete" output port. Ignore my below comment, I'm a numpty!

 

Hi niels,

 

I've tried this approach but the correct answers come out of the "Summary" port - and only have the 2 fields, leaving the others out of the output (as shown). Is there something I'm missing?

 

To make things more complex the dates I've been given have only 1 of them with data in, which means the output is now incomplete - but that's for another time lol